A common code question I receive is whether or not stairs are permitted to be open on both floors.  All stairs are required to be enclosed unless noted otherwise per the Chicago Building Code (CBC) 7(15-8-140). Stairway enclosures shall not be required in buildings of Types I-A, I-B, and I-C Construction for stairs from the second floor to the main exit floor and serving the second floor only, except in Hazardous Use Units, in Multiple Dwellings and in Institutional Units where habitable rooms are located on the second floor and stairs in Mercantile and Business Units from a basement sales space to the main exit floor level, constituting not more than fifty percent of the total required width of exit stairs. Stairway enclosures shall not be required in buildings of any type of construction in Residential Units, stairs serving one dwelling unit only and entirely contained within such dwelling unit, in Assembly Units, stairs connecting any balcony level with the main floor level and in all occupancies, stairs connecting a mezzanine floor to the floor immediately below.

While commonly incorporated into multi-level tenant floors, an open stair between these floors is not specifically permitted per CBC.  However, two years ago, an interpretation to the CBC code requirements was posted on the Department of Buildings website that allows for additional stairs to be open as long as they meet the following noted parameters.

Stairway enclosure shall not be required for the stairway serving any two floors in buildings of Type I-A, I-B, and I-C construction with the following conditions:

1. The entire building is protected by an automatic sprinkler system.

2. The open stairway is not used as a required exit, except where permitted by the

Section 7(15-8-140)(b)&(c).

3. The occupancy of the floors served by the open stairway is not Hazardous Use,

Multiple Dwellings or Institutional Use.

4. All shafts within 100 feet horizontal distance from the unenclosed stairway opening, on both levels, have minimum one (1) hour enclosure, except the shafts for pipes and ducts passing from one floor to the other as per section 7(15-8-160).

This ruling is based on the fact that Section 7(15-8-140)(b) allows stairway between two floors, between the ground floor and the second floor, without any enclosure, and with the life safety features and restrictions in place, it shall be permitted between any two floors of a Type I building.  Stairs that are open for more than one floor would have to comply with the requirements for Atriums or apply to the Committee on Building Standards and Tests.

Submitted by Leah Riley

Related Posts:

Tags: , , , ,

Leave a Reply

"Burnham is a first-rate operation. I rely on them to coordinate many of the permit-related tasks that I am too busy to do myself. I draw on their knowledge on changing municipal requirements, proactive problem solving and would definitely recommend them to others."
Rich Neubauer,
McDonald's
"I've had great success with Burnham for permit expediting, and recently learned they offer code consulting. They are great in meetings and provide excellent reports supported by detailed research and experience. I will use them whenever I have code issues on a project."
Jeff Kennedy,
Centaur Construction
"I like Burnham because their response time is terrific. They're professional with a systematic approach and solid corporate infrastructure - and their web-based system shows me exactly what is happening with my permits at all times."
Tom McCloskey,
The Related Companies, L.P.
"Working with Burnham makes the best use of my resources. It would be too costly for me to have staff who know as much as they do about the permit process."
Mike Moravek,
The John Buck Company
"Burnham is always a vital part of our Project Team. Their level of service and professionalism far surpasses their competition. The first call I make when a new project comes in is to Burnham."
Gregg Navins,
OMARA Organization, Inc
"We have tried other permit services in the past but only Burnham delivers the level of detail, follow through and accountability necessary to be successful in today's complex permit acquisition arena."
Dave Morgan,
The Body Shop
"Speed and efficiency are paramount, we aren't looking for just another layer of project management. Burnham gets the process due to their strong knowledge of jurisdictional requirements, and excellent working relationships with municipal staffs."
Glenn D. Middleton,
Design Forum
"We have come to rely heavily on Burnham's expertise... they have developed a professional consulting practice that we are proud to be associated with."
Michael T Clune,
Clune Construction Company